Fabra Elementary was designed to convert corridors to collaborative, inspiring, and immersive learning environments.
The 99,000-square-foot K-5 school opened on time and on budget, August 2016.
Area: 97,336 SF
Cost: $21,622,579
Price S/F: $222.14/SF
Bid: 2015
Completed: 2016
Campus Entrance Security Upgrades
- Security vestibules constructed on all elementary campuses.
Air Condition Elementary Gyms
- All five elementary gyms air conditioned to improve health and security.
Classroom Technology Enhancements
- Infrastructure for wireless capacity enhanced on all campuses
- Array of desktop, laptop and mobile devices deployed to achieve ratios of 5:1 in elementary classrooms, 3:1 in secondary classrooms.
- Smartboards added to every elementary classroom and select secondary classrooms.
BMS North Classrooms & Gymnasium
- New classroom wing, CTE workshop, competition gymnasium and upgraded boys and girls locker rooms and physical education spaces constructed.
BMS South Math/Science Classrooms
- New classrooms and labs constructed.
Curington Elementary Expansion/Renovation
- Cafeteria addition, kitchen expansion, administrative offices constructed.
- Updates to classrooms throughout the campus.
Boerne High School Expansions and Upgrades
- Career & Technical Education facility constructed.
- Band facilities expanded. Culinary Arts kitchen, science classrooms constructed.
- Gymnasium updated; new visitors’ fieldhouse and new baseball/softball concessions building constructed.
Transportation/Warehouse Expansion
- District warehouse and bus maintenance facility expanded to meet demand.
Purchase New Buses, Support Vehicles
- 22 new buses purchased to replaced aging vehicles; district-wide support fleet enhanced.
More About Bond 2013 Committees
-
- John Atchison
- David Boggan
- Mike DeLeeuw
- Henry Gideon
- Joe Granados
- Heberto Hinojosa
- Baron Houser
- Kristen Kurtz
- Jerry Lamping
- David Limon
- Mike Lopez
- Jim Martin
- Kent Niemann
- Mark Oppelt
- Israel Pena
- Daniel Perez
- Gay Polito
- Rich Sena
- DeVan Watts
- Andra Wisian
- Crisanne Zamponi
-
-
Dale Adams
-
David Boggan
-
Brian Combs
-
Thom Dunaway
-
Richard Elkins
-
Jeff Jaime
-
George Monroy
-
Brad Morrison
-
Teri Nail
-
Donna Sharp
-
Steve Stewart
-
Julie Turner
-
Project Oversight Files
-
BMS N Phasing Additions Renovations 111913pdf
-
BOERNE HS PRESENTATION 11315pdf
-
Bond Budget Contingencies 10 7 14pdf
-
Bond Budget Contingencies ET ALL APRIL 1 2014 ver 2 0pdf
-
Bond Oversight agenda 030315pdf
-
Bond Project Oversight Meeting Notes 1 14 14pdf
-
Bond Project Oversight Meeting Notes 1 14 15pdf
-
Bond Project Oversight Meeting Notes 10 7 14pdf
-
Bond Project Oversight Meeting Notes 3 20 14pdf
-
Bond Project Oversight Meeting Notes 3 3 15pdf
-
Bond Project Oversight Meeting Notes 4 22 14pdf
-
Bond Project Oversight Meeting Notes 6 10 14pdf
-
Bond Project Oversight Responsibilities 2013pdf
-
chs bond projects diagram 12 13pdf
-
curington bond drawings 901013pdf
-
New FES Design Planning Teampdf
-
oversight comm shw 032014pdf
-
ProjectCom Meeting Notes 091013pdf
-
ProjectCom Meeting Notes 111913pdf
-
Projected Cost Report 030315pdf
-
Projected Cost Report 091615pdf
-
School Campus Bond Projects Summer 2014pdf
Technology Oversight Files
-
BMS N Phasing Additions Renovations 111913pdf
-
BOERNE HS PRESENTATION 11315pdf
-
Bond Budget Contingencies 10 7 14pdf
-
Bond Budget Contingencies ET ALL APRIL 1 2014 ver 2 0pdf
-
Bond Oversight agenda 030315pdf
-
Bond Project Oversight Meeting Notes 1 14 14pdf
-
Bond Project Oversight Meeting Notes 1 14 15pdf
-
Bond Project Oversight Meeting Notes 10 7 14pdf
-
Bond Project Oversight Meeting Notes 3 20 14pdf
-
Bond Project Oversight Meeting Notes 3 3 15pdf
-
Bond Project Oversight Meeting Notes 4 22 14pdf
-
Bond Project Oversight Meeting Notes 6 10 14pdf
-
Bond Project Oversight Responsibilities 2013pdf
-
chs bond projects diagram 12 13pdf
-
curington bond drawings 901013pdf
-
New FES Design Planning Teampdf
-
oversight comm shw 032014pdf
-
ProjectCom Meeting Notes 091013pdf
-
ProjectCom Meeting Notes 111913pdf
-
Projected Cost Report 030315pdf
-
Projected Cost Report 091615pdf
-
School Campus Bond Projects Summer 2014pdf